The New Autoroute 30 project has been one of the most important infrastructure projects of the last ten years in Quebec. On several levels, Groupe Brunet has been a leading player in its realization.
The project in figures :
- Global project worth 1,5 billion
- 12 contracts for Groupe Brunet in many disciplines, in particular:
- 357 pillars and 72 pier caps manufactured for the Madeleine-Parent Bridge
- 1000 culverts, manholes and sumps for drainage as well as access shafts
- 1 pumping station of 100 feet high x 10 meters in diameter
- 10 km of New Jersey concrete slides
- 22,000 loads of ready-mixed concrete for dozens of structures including the Serge-Marcil Bridge
- 6 km of noise barriers